Mar 27, 2022

Chimney installation and ladder construction deployment

Leave a message

Chimney installation and ladder construction deployment


1. The main construction process


Specifically, no scaffolding, high-altitude hanging operation is used for chimney installation and ladder construction.


2. Construction process


  Prepare to measure → stair welding production → anti-rust treatment → support column installation → tie rod installation → tread plate installation → installation of railings → completion.


Chimney installation and ladder construction measures


1), construction safety and technical measures:


1. First of all, the construction personnel climb to measure the specific construction size. They need to be cautious when climbing. At the same time, they should check the safety performance and firmness of the original ladder and platform of the chimney to prevent the installation of the ladder platform from the chimney. There are potential safety hazards such as weak structure, desoldering and corrosion.


2. The production of all the steel components of the folding ladder platform is completed by welding on the ground. After the ground is finished, the anti-rust primer and top coat are painted once.


3. High-altitude hanging operation method: Fix the high-altitude work rope at the place where the top platform of the chimney is firm, and then put the work rope (ф18) and safety rope down along the chimney elevation, and use the seat-type climbing board to slide down the chimney wall for construction. During the suspension operation, the operator must wear double insurance, one safety rope (working rope) is tied to the chimney platform, one safety rope is tied to the ladder (or embedded parts), and a special person must be sent to the ladder (or platform) to take care of the insurance. rope.


4. Hanging plate composition:


1) Suspension rope (aerial work rope, scientific name nylon rope, diameter 18 mm)


2), auxiliary rope (safety protection rope): scientific name nylon rope, diameter 16 mm)


3) Hanging board (made of ash wood)


4), U-shaped crab buckle (steel)


5), seat belt The above 5 kinds are assembled into a sitting high-altitude hanging plate for construction.


 2) Installation of chimney ladder:


1. Using the method of high-altitude suspension operation, after fixing the four beams and columns (10*) in vertical columns according to the size measured on site, weld the bracing (8*) at the same time, then connect the steel plates on both sides, and then weld the stair treads one by one ( 0.5 cm thick checkered plate), from bottom to top, work in sequence, step by step to the 30-meter part of the chimney.


2. The installation of the folding ladder railing is from bottom to top, and it is welded and installed on the platform board.


3. The chimney installation ladder must be welded firmly during the welding construction, and no leakage welding shall be allowed. When installing the ladder, pay attention to keeping it beautiful and horizontal and vertical.


    3) Completion: After all construction procedures are completed, the construction personnel should be organized to evacuate the construction site in a safe and orderly manner, so that Party A can arrange relevant production and work, and truly clear the site after the completion of the construction.


Chimney installation and ladder construction progress plan


1. According to the actual situation of the project, formulate goals, divide the labor for implementation, grasp the construction progress and construction procedures, and arrange scientifically; rationally organize and improve the operation of the project on the premise of ensuring the quality of the project.


2. Carry out the construction in a standardized and orderly manner in accordance with the specific regulations of the project. In the progress of the system construction plan, the main key processes should be well grasped, and the progress and plan should be implemented layer by layer, and specific to each construction worker, so that they can be dismantled and guaranteed quality. To ensure the smooth progress of the project and to ensure that the overall project plan is completed on schedule in 23 sunny days.