Specific specifications for chimney reinforcement?
Specific Specifications for Chimney Reinforcement
1. For the personnel involved in the construction of the chimney project, when the chimney project is carried out with three-dimensional crossing operations. It is necessary to carry out technical training and safety education, so that they can understand the construction characteristics of this project, be familiar with the requirements and the safety technical operation rules of the position, and can only work after passing the assessment. The main construction personnel should be relatively fixed.
2. The chimney construction personnel should first go through the medical examination of the medical department to prove that the physique is suitable for those who work at heights before they are allowed to work. The construction personnel of the chimney operating platform must undergo regular physical examinations, and those suffering from high blood pressure, heart disease, anemia, epilepsy and other diseases that are not suitable for working at heights are not allowed to work on the operating platform after being diagnosed by the doctor.
3 During the construction of the chimney, the local meteorological station and station should be contacted frequently, and the construction must be stopped when encountering thunderstorms and strong winds of level 6 and above. Take protective measures before the shutdown, evacuate the personnel on the operating platform, organize, fix and protect the equipment, tools, scattered materials and movable planks, etc., and immediately cut off the power supply to the operating platform after all personnel are evacuated.
4 The construction site of the chimney must have the conditions of leveling the site, unobstructed roads, electricity and water supply, and the site layout should be carried out according to the general plan of the construction organization design.
5 Construction danger warning areas must be delineated around the buildings (structures) under construction. The distance from the cordon to the building (structure) should not be less than 110 meters and not less than 10m of the height of the construction object. If the requirements cannot be met, effective safety protection measures should be taken.
6 The danger cordon should be set up with fences and obvious warning signs, and the exit population should be specially guarded and a guard system should be established.
7. Temporary buildings such as power supply, office and sanitary facilities, and bulk materials at the construction site should be arranged outside the danger warning line.
8 Safety protection sheds with a height of not less than 2.5m should be erected for exits, ground passages and mechanical operation places of buildings in the danger warning zone.
An isolation shed should be set up between the upper and lower working surfaces. All kinds of pulling wire ropes, pulley devices, pipes, cables and equipment should take protective measures.