In the flue gas desulfurization (FGD) system of large thermal power generating units, the flue gas desulfurization baffle door is an important equipment for the entry and exit of the desulfurization device. The desulfurization baffle door adopts a single-axis double baffle structure with sealed air. A nickel alloy sealing sheet is arranged around each baffle blade, and the sealing air inlet on the body of the baffle door is provided with a sealing air valve, which is mechanically linked with the baffle door. When the flue gas baffle is open, the sealing damper is closed; the flue gas baffle is closed and the sealing damper is open. When the baffle door is closed, seal air is injected between the double-layer blades to effectively isolate the front and rear media. The desulfurization baffle door can operate safely for a long time, ensuring flexible rotation, opening and closing, and no jamming under working conditions. To ensure tightness and leakage, the sealing efficiency is 100% (zero leakage rate).
Do you really understand the precautions for the installation and use of the electric actuator of the desulfurization baffle door? Let's listen to your specific explanation.
1. The damper door must be closed before installing the actuator.
2. Manually operate the actuator to the closed position.
3. Actuator installation procedure: 1) Remove the position indicator cover, and check whether the keyway position of the shaft sleeve in the secondary reducer of the actuator is consistent with the position of the drive shaft key of the baffle door. If not, the secondary reducer can be removed The inner sleeve is rotated through an angle to make the keyway consistent with the key position on the drive shaft. If there is a small deviation, you can manually operate the actuator to turn the shaft sleeve to the desired position; 2) Check whether there is burr caused by the collision between the shaft head of the drive shaft and the key, if available, install the actuator after polishing with sandpaper; 3 ) When the actuator is installed, it needs to be perpendicular to the drive shaft and push it by hand (the size of the inner hole of the actuator bushing is generally 10-20um larger than that of the drive shaft); if it is difficult to push, you can enter the shaft head on the reducer bushing Then use long bolts to pass through the bolt holes on the actuator mounting plate to connect with the bolt holes on the reducer, gradually tighten the bolts symmetrically and evenly, and install the actuator in place. During this process, it should be noted that the depth of the bolts entering the reducer does not exceed 20mm, so as not to damage the internal sector gear of the reducer.
4. The actuator base plate (installation fixing plate) is oval, with three bolts on each end for fastening. After the bolts are loosened, the seat plate has an adjustment amount of about 10mm up, down, left and right. If the actuator mounting hole is misaligned with the seat plate mounting hole, adjust the position of the seat plate so that the center coincides and then tighten all the connecting bolts.
5. After the above work is completed, the fixing bolts at both ends of the actuator seat plate must be tightened.
6. After the above steps, manually operate the actuator to the open position (marked as''), and check whether the position of the baffle door meets the requirements. If the opening is insufficient, the mechanical limit bolt on the actuator can be screwed out , And then open the door to the required position, then screw in the mechanical limit bolt, after touching the side of the sector gear, withdraw one circle and lock it with the back cap.
7. Manually operate the actuator to the "off" position and check whether the baffle door is closed in place. If it is not in place a little, you can adjust the mechanical limit bolt in the "close" direction. The method is the same as above.
8. When the baffle door is in the fully closed position, check whether the sealing of the door is good, and adjust the sealing to meet the requirements when it is not good.
9. After the above work is completed, the actuator can be powered on for electrical debugging.